How to dry hanging stone design and installation of ceiling panels contacts

stone Cladding, to different parts of the ceiling panels of a serious, thoughtful design, draw contacts diagram, the designer guidance in the construction site.

First, the load-bearing steel keel ceiling stone load can not be passed to the main structure of the glass curtain wall, stone hanging steel keel only "must attack."

Secondly, in the rib plate glass and stone ceiling junction fastener can not be fixed from the side of the stone, so to a "prepared by Bolt," Stone Cladding law. From an economic point of view and the progress of the project must be galvanized common expansion bolts, expansion bolts ordinary tethered to a solid slate will have a certain depth, the expander to work, each baffle spacing (the size of very important), but also marble, because the sheet metal division depends on the distance between ribs; if it is in accordance with the glass curtain wall construction design, be sure to review the size; otherwise, Stone Cladding design submission, the construction side in Figure lofting, Click image processing stone supplier, size, plate waste are not allowed to lead and influence the duration.

Stone Cladding specific construction process is as follows:

1, Stone Cladding should be strictly according to the drawings, the steel frame construction, suspended ceiling panels in place, may be appropriate to open a bigger hole so that when the trim panel in place.

2, pore size review in place, setting out to determine the location and the side plate off the back of the drill hole.

3, the material side of the drill diameter of 6mm, 30mm deep hole two.

4, the back plate hole diameter 10mm, using pins to ensure the drilling depth 40mm, 4 holes each plate.

5, clean the dust inside the hole to hole into the amount of the AB glue; the expander cut into 4 cm length (this can be pre-made), find into the expansion bolts, drilling with casing Slate the expander holes until flush with the stone; then pad, spring washer, nut tightening.

6, the hanging board in place, install the first piece of board, with hanging wire and pallets adjustment, fixed; then install the side of the fastener, the pin; and then install a second plate, aligning the side hole and bolt hole pin adjustment in place with flat washer, spring washer, nut tightening. Installation of the remaining board material accordingly.

7, Stone Cladding after installation of ceiling cleaning, gluing.